Friday 6 March 2015

And so it begins!


Builder - Hotondo
Plan - The Jamieson 222
Land - 1200sqm

Today marked the start of an exciting journey as we build our first family home. It was such a nice surprise to venture to the land today to find that they had already scraped it, considering I was told that would be happening sometime next week. We were off to a good start with it only taking 3 weeks for council approval, then to find that they are ahead of the schedule already, I'm pretty impressed. 

So the timeline so far:

16th January 2015 - Land settlement day!
5th February 2015 - The sign went in this morning!  
9th February 2015 - Plans submitted to council.
10 February 2015 - Council requested copy of Contract of Sale as their records had not been updated for some reason.
4th March 2015 - Builder advised the plans had been approved through council (...and it was my birthday). 
6th March 2015 - Sometime between 4th & 6th  March the site scrape happened.